Project Name |
National Alabama Corporation |
| |
|
Background
Information:
|
- Location: Cherokee/Muscle Shoals, Alabama
- Contract Value: Over $5 million
- Partnered With: Infosys - A Division of OESCO, an FEC Partners
|
| |
|
Description
|
- All backbone data, security and WIFI infrastructure
for this 1.9 million square foot manufacturing facility
making railroad cars for companies worldwide.
- Installation of 19 MDF and IDF closets for network
system components which included equipment
racks, ladder trays and grounding buss for this facility.
- Installation of signal grounding system
consisting of a 4/0 AWG ground loop and 2" PVC conduit
to tie the communication MDF and IDF closets
together for a redundant signal ground.
- Installation of more than a mile of Air Blown Fiber
Tubing Pathway to provide raceway for the network system
fiber optics cabling. The majority of the pathway was 19
Tube raceway terminating in TDU cabinets near each MDF
or IDF closet.
- Installation of several miles of 18 strand, Air
Blown Fiber Cabling to provide a redundant fiber link
system for the facility network.
- Installation of over half a million feet of CAT6
Augmented cable for the Data Communications network
system includeding conduit and cabling for
the drops for Data, Phone, Security and
WIFI systems throughout the plant.
- Installation of all power circuits required for
network system equipment throughout the entire facility.
|
| |
|
Challenges:
|
- Fiber and grounding system was to be installed as
the General Contractor was finalizing the building
construction and in a three month time frame. We beat
the scheduled completion date.
- Installation of Data Communications system cabling
as the Owner was in the process of commissioning their
equipment which meant that portions of the process was
operable.
- Installation of the Security and WIFI cabling
systems while the plant was in operation which meant
multiple shifts required to meet the schedule.
|
| |
|
Summary:
|
This was a successful job for White Electrical
contractors and our
partner, Infosys - A Division of OESCO. We completed each
phase of the work on time or early and within budget to
enable the owner to utilize his network system for operation
of the facility. |
| |
|